Energy Projects Near You

Solar, wind and battery projects near Boat of Garten (PH24)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of PH24 (Highland): none of them is pending, approved or operational. The largest scheme is Boat of Garten (49.9 MW battery storage, application withdrawn on 28 February 2022), 1.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of PH24

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Boat of Gartenbattery storagebattery storage49.9application withdrawnupdated Mar 2022Feb 2022—Mar 2022Highland1.1

Distance from the average position of the PH24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.