Boat of Garten (49.9 MW battery storage)

Boat of Garten is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 28 February 2022; the record was last updated on 1 March 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application withdrawnstatus in REPD
1 March 2022record last updated
Highlandcouncil area

Planning timeline

DateStage
15 February 2022Application submitted
28 February 2022Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application withdrawn
Record last updated
1 March 2022
Operator or applicant
Whirlwind Energy Storage Limited
Planning authority
Highland
Planning application reference
22/00601/FUL
Address (REPD)
380M West Of East Croftmore Boat Of Garten
Council area (by location)
Highland
Name in REPD
Boat of Garten - Battery Energy Storage
REPD reference
10700

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.2546, -3.7269).