Energy Projects Near You

Solar, wind and battery projects near Swansea (SA3)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA3 (Swansea): 3 approved but not yet running, 3 operational. The largest live scheme is Parc Solar Caenewydd (46 MW battery storage, under construction since 1 May 2026), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
0awaiting a decision
3approved, not running
3operational

Projects within 10 km of SA3

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Webbsfieldsolar farmsolar farm1refused on appealupdated May 2015Jun 2014refused Sep 2014May 2015Swansea3.0
Killan Farm Solar Array Extenssolar farmsolar farm1operationalupdated Jan 2018Jul 2015granted Dec 2015Jan 2018Swansea5.1
Timet UKwind farmwind farm2refusedupdated Jul 2005Sep 2003refused Aug 2004Jul 2005Swansea6.4
Cockett Valleysolar farmsolar farm4operationalupdated Oct 2017Dec 2014granted Aug 2015Oct 2017Swansea6.8
Parc Solar Caenewyddbattery storagebattery storage46under constructionupdated Jun 2026Jun 2024granted Dec 2024Jun 2026Swansea8.6
Parc Solar Caenewyddsolar farmsolar farm42under constructionupdated Jun 2026Jun 2024granted Dec 2024Jun 2026Swansea8.6
Dura Park Bynea Industrial Siterooftop solarrooftop solar1.4operationalupdated Jun 2016Oct 2015granted Dec 2015Jun 2016Carmarthenshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hazel Court, Sketty Parkrooftop solarrooftop solar—refusedupdated May 2023Apr 2023refused May 2023May 2023Swansea5.7
Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025May 2025granted Jun 2025May 2025Swansea9.7
Heol Y Mynydd Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2026Feb 2026refused Apr 2026Jun 2026Swansea9.9

Distance from the average position of the SA3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4012142
Rooftop solar200110
Wind farm100010
Battery storage3020146.2

MW in pipeline: pending, approved and under-construction capacity.

How Swansea decides solar, wind and battery applications

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

All projects in Swansea

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.