Energy Projects Near You

Solar, wind and battery projects near Isleworth (TW7)

95 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TW7 (Hounslow): 5 are waiting for a planning decision, 78 approved but not yet running, 6 operational. The largest live scheme is Long Lane, Stanwell (49.9 MW battery storage, approved on 18 July 2025, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

95projects within 10 km
5awaiting a decision
78approved, not running
6operational

Projects within 10 km of TW7

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Western International Marketrooftop solarrooftop solar1.7operationalupdated May 2016Jul 2015granted Sep 2015May 2016Hounslow5.6
Premier Park Road - Photovoltaic Systemrooftop solarrooftop solar1.4approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Brent8.4
Unit F, 6, Premier Park Roadrooftop solarrooftop solar1.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Brent8.4
Walton WTW PVsolar farmsolar farm1.8operationalupdated Oct 2013——Oct 2013Elmbridge8.8
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Hammersmith and Fulham8.8
Sipson Roadsolarsolar6.2refusedupdated Nov 2014Jun 2014refused Oct 2014Nov 2014Hillingdon9.2
Land south of Holloway Lanesolar farmsolar farm5application withdrawnupdated Jan 2016Jul 2015—Jan 2016Hillingdon9.3
Long Lane, Stanwellbattery storagebattery storage49.9approved, not builtupdated Jul 2025Dec 2024granted Jul 2025Jul 2025Spelthorne9.3
London’s Queen Elizabeth II reservoirfloating solarfloating solar6.3operationalupdated Jul 2016——Jul 2016Kingston upon Thames9.4
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Thames College, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Hounslow0.5
West Middlesex Hospital, Twickenham Roadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Sep 2024granted Nov 2024Jan 2025Hounslow0.8
West Middlesex University Hospital,Twickenham Roadrooftop solarrooftop solar—approved, not builtApr 2026granted Jun 2026—Hounslow0.8
West Cross Industrial Park Shield Driverooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Hounslow1.6
Alexandra Junior Schoolrooftop solarrooftop solar0.1approved, not builtupdated Dec 2021Jul 2021granted Sep 2021Dec 2021Hounslow1.7
Shield Drive Industrial Estaterooftop solarrooftop solar—approved, not built may be out of dateupdated Sep 2022May 2022granted Jun 2022Sep 2022Hounslow1.8
Twickenham Trading Estate, Rugby Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Richmond upon Thames1.9
Chertsey Roadrooftop solarrooftop solar0.2refusedupdated Apr 2024Jan 2024refused Mar 2024Apr 2024Richmond upon Thames2.0
Kneller Hall Schoolrooftop solarrooftop solar0.2under constructionupdated Jan 2026Dec 2022granted Oct 2025Jan 2026Richmond upon Thames2.2
Big Yellow Self Storage, Staines Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Hounslow2.7
Brentford Works, Great West Road - Masterplanrooftop solarrooftop solar0.2approved, not builtupdated Jul 2026Nov 2024granted Jun 2026Jul 2026Hounslow3.7
Ham Close - 452 Houses, Flats & Leisure Centrerooftop solarrooftop solar0.4under constructionupdated Apr 2024Jun 2022granted Mar 2023Apr 2024Richmond upon Thames4.0
Heathrow Gatewayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Hounslow4.1
Great Western Industrial Park, Armstrong Wayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Ealing4.1
Prologis Park, Unit Brooftop solarrooftop solar1refusedupdated Jul 2024May 2024refused Jul 2024Jul 2024Hounslow4.1
University Of West London Solar Photovoltaic & Ground Source Heat Pumprooftop solarrooftop solar0.2application withdrawnupdated Dec 2021Jul 2021—Dec 2021Ealing4.3
University Of West London Solarrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Jul 2021granted Nov 2021Dec 2021Ealing4.3
Hampton Business Park, Bolney Way- Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Aug 2022granted Oct 2022Jan 2022Hounslow4.9
Spur Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Hounslow5.0
Sainsburys Supermarkets, Uxbridge Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Richmond upon Thames5.0
David Lloyd Racket Club, Southall Lanerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Hounslow5.0
Falcon House, Central Way - Photovoltaic Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Hounslow5.1
Sainsburys Supermarkets, Essex Placerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Hounslow5.4
Devonhurst Placerooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022Hounslow5.4
Southall Lane Waste Depotbattery storagebattery storage—operationalupdated Nov 2022Jun 2017—Nov 2022Hounslow5.5
International Trading Estate, Trident Way - Data Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Mar 2025granted Dec 2025Jan 2026Ealing5.6
Western International Market (WIM) Sitebattery storagebattery storage0.2operationalupdated May 2016Dec 2015—May 2016Hounslow5.6
Geodis, Faggs Roadrooftop solarrooftop solar0.8approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022Hounslow5.7
Hatton Cross Underground Station, Southern Perimeter Road -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Hillingdon6.1
Pasadena Centre, Pasadena Closerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Apr 2023Nov 2022granted Mar 2023Apr 2023Hillingdon6.3
Lombardy Retail Park, J Sainsbury Plcrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Hillingdon6.8
Yeading Infant School, Carlyon Road Solar PV Systemsrooftop solarrooftop solar0.1application withdrawnupdated Sep 2024Jul 2024—Sep 2024Hillingdon7.0
Light House, Western Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Ealing7.5
Unit 5, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent7.6
Unit 1, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent7.6
Unit 6, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent7.6
Unit 4, Origin Business Park, Rainsford Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Brent7.7
Unit 2, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent7.7
Ealing Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Brent7.7
Unit 3, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Ealing7.7
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Hillingdon7.8
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Hillingdon7.8
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Hillingdon7.8
Belazu Ingredient Company, Long Driverooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Ealing7.9
Sergo Park Greenford Central, Phase 1A - Industrial, Warehouse & Officesrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Jul 2024granted Jan 2025Feb 2025Ealing7.9
Swallowfield Wayrooftop solarrooftop solar0.4approved, not builtupdated Jun 2022May 2022granted Aug 2022Jun 2022Hillingdon7.9
Prologis Greenford DC1, Oldfield Lane Northrooftop solarrooftop solar0.3application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Ealing8.0
Nucleus, Central Wayrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Brent8.0
Nucleus, Central Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Brent8.0
Edwards Yard, Alperton - 581 Apartments & Commercial Unitsrooftop solarrooftop solar0.7approved, not builtupdated May 2022Sep 2020granted Jan 2022May 2022Brent8.1
Heathrow Flightpath Car Park, Bath Roadbattery storagebattery storage—approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Hillingdon8.1
Phoenix Fitness Centre, Phoenix Closerooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Hammersmith and Fulham8.2
Charlie Bighams, Mcnicol Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Dec 2023granted Feb 2024Jan 2024Brent8.2
Tudor Estate, Abbey Roadrooftop solarrooftop solar—application submittedupdated May 2026Apr 2026—May 2026Brent8.2
Premier Park Road, Unit 4rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent8.3
Premier Park Road, Unit Brooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent8.3
Central Wayrooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted May 2025Jul 2025Brent8.3
Prop House, Abbey Roadrooftop solarrooftop solar0.6approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Brent8.3
Premier Park Road, Unit 7-8rooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent8.4
Premier Park Road, Unit 1rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent8.4

26 more projects not listed (furthest or smallest).

Distance from the average position of the TW7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300200
Rooftop solar865761228.6
Solar100010
Floating solar100100
Battery storage4022049.9

MW in pipeline: pending, approved and under-construction capacity.

How Hounslow decides solar, wind and battery applications

ApplicationsHounslowUK
Decided applications (solar, wind, battery)2210,236
Refused3 (14%)19%
Solar refused3 of 2212%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Hounslow

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TW7, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.