Energy Projects Near You

Solar, wind and battery projects near Rickmansworth (WD3)

26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WD3 (Three Rivers): 6 are waiting for a planning decision, 14 approved but not yet running, 2 operational. The largest live scheme is Hilfield Lane, Aldenham (170 MW battery storage, approved on 16 January 2026, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26projects within 10 km
6awaiting a decision
14approved, not running
2operational

Projects within 10 km of WD3

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
David Lloyd Leisure, Ducks Hill Roadrooftop solarrooftop solar1refusedupdated Jul 2023Jun 2023—Jul 2023Hillingdon4.7
Langleybury Film Hubrooftop solarrooftop solar3application submitted may be out of dateupdated Dec 2022Oct 2022—Dec 2022Three Rivers5.5
Gerrards Cross Sewage Treatment Worksbattery storagebattery storage20application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021Buckinghamshire8.3
Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagesolar farmsolar farm22approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026Dacorum8.3
Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagebattery storagebattery storage10approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026Dacorum8.3
Pinstone Farm, Oxford Roadbattery storagebattery storage60application submittedupdated Sep 2025Jul 2025—Sep 2025Buckinghamshire8.8
Elstree Substation, Hilfield Lanebattery storagebattery storage400application withdrawnupdated Nov 2024Nov 2023—Nov 2024Hertsmere9.8
Hilfield Lane, Aldenhambattery storagebattery storage170approved, not builtupdated Feb 2026Feb 2025granted Jan 2026Feb 2026Hertsmere9.9
Smaller schemes under 1 MW, mostly rooftop solar (18)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Royal Masonic School, Rickmansworth Parkrooftop solarrooftop solar0.1application submittedApr 2026——Three Rivers0.6
The Tropical Marine Centre, Solesbridge Lanerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Three Rivers1.6
Rickmansworth School, Croxley Greenrooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023Three Rivers1.9
York House School, Sarratt Roadrooftop solarrooftop solar0.3application withdrawnupdated Jan 2026Sep 2025—Jan 2026Three Rivers2.4
Bullsland Farmsolar farmsolar farm0.3approved, not built may be out of dateupdated Feb 2022May 2021granted Jan 2022Feb 2022Three Rivers3.5
Mount Vernon Hospitalrooftop solarrooftop solar—operationalupdated Jan 2022Jul 2021granted Nov 2021Jan 2022Hillingdon4.3
Northwood Health And Racquet Club, Ducks Hill Roadrooftop solarrooftop solar0.3application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Hillingdon4.7
Northwood College, Maxwell Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2023May 2023granted Jul 2023Jun 2023Hillingdon5.6
Denham Grove Hotel, Tilehouse Lanerooftop solarrooftop solar0.3refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026Buckinghamshire5.7
Tims Dairy, Denham Lanerooftop solarrooftop solar0.2application submittedMay 2026——Buckinghamshire6.1
GE Healthcare, Pollards Woodrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Buckinghamshire6.2
Tesco Stores Limited, Lower High Streetrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Nov 2024granted Jan 2025Mar 2025Watford6.6
Micro House, Bury Street Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Hillingdon7.2
Kingsway North Orbital Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Jan 2022granted Mar 2022Feb 2022Watford7.9
Woodside Leisure Centrerooftop solarrooftop solar0.3operationalupdated Mar 2025Dec 2024granted Jan 2025Mar 2025Watford8.2
David Lloyd Leisure Club, Hartspring Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Hertsmere8.3
C P House, Otterspool Wayrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Hertsmere8.4
The Mount Hmp, Molyneaux Avenuerooftop solarrooftop solar—approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Dacorum9.6

Distance from the average position of the WD3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2020022.3
Rooftop solar19410225.5
Battery storage52200260

MW in pipeline: pending, approved and under-construction capacity.

How Three Rivers decides solar, wind and battery applications

Three Rivers has 3 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Three Rivers

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WD3, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.