Energy Projects Near You

Blackpark Energy Storage (30 MW)

Blackpark Energy Storage is a 30 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 December 2020, not yet built; the record was last updated on 12 January 2021. REPD also records that the planning permission expired on 15 December 2023, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtmay be out of datestatus in REPD
12 January 2021record last updated
Highlandcouncil area

REPD also records that the planning permission expired on 15 December 2023, so the project may not go ahead in this form.

Planning timeline

DateStage
14 July 2020Application submitted
15 December 2020Planning permission granted
15 December 2023Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
12 January 2021
Operator or applicant
Shires Hamilton
Planning authority
Highland
Planning application reference
20/02589/FUL
Address (REPD)
Black Park Farm, Nairn,
Council area (by location)
Highland
Time to decision
22 weeks
REPD reference
8105

Earlier applications for this site

ApplicationMWSubmittedOutcome
Blackpark Farm 19/00702/FUL2028 February 2019replaced by a revised application

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Househill House, Househillbattery storage49.9approved, not built0.7
Grigorhill Cottage, Grigorhillbattery storage49.9approved, not built1.3
Blackpark Housebattery storage30approved, not built1.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5708, -3.8456).