Blackpark House (30 MW battery storage)

Blackpark House is a 30 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 October 2025, not yet built; the record was last updated on 9 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
9 December 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
16 December 2024Application submitted
14 October 2025Planning permission granted
14 October 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
9 December 2025
Operator or applicant
Anesco
Planning authority
Highland
Planning application reference
24/05019/FUL
Address (REPD)
South Of Blackpark House Nairn
Council area (by location)
Highland
Time to decision
43 weeks
Name in REPD
Blackpark House - Battery Storage
REPD reference
12383

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grigorhill Cottage, Grigorhillbattery storage49.9approved, not built0.6
Blackpark Energy Storagebattery storage30approved, not built1.9
Househill House, Househillbattery storage49.9approved, not built2.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5663, -3.8144).