Energy Projects Near You

Blackstone Edge (7.5 MW wind farm)

Blackstone Edge is a 7.5 MW wind farm project in Barnsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2013; the record was last updated on 4 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
4 April 2013record last updated
Barnsleycouncil area

Planning timeline

DateStage
1 November 2006Application submitted
26 May 2009Planning permission granted
1 July 2012Construction started
1 March 2013Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
4 April 2013
Operator or applicant
Ventient (formerly Infinis)
Planning authority
Barnsley
Planning application reference
2008/0171
Turbines
3
Address (REPD)
Blackstone Edge, Penistone
Council area (by location)
Barnsley
Time to decision
134 weeks
REPD reference
3958

Who decides

ApplicationsBarnsleyUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused0 of 1312%
Onshore wind refused2 of 645%
Battery storage refused0 of 516%
Median time from submission to decision21.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spicer Hill Wind Farm Extensionwind farm6.9refused on appeal0.8
Spicer Hill Wind Farmwind farm6.9operational1.2
Dearne Head Wind Farmwind farm8refused2.0
Hazleheadwind farm6operational2.1
Royd Moorwind farm5.9operational2.7
Tofts Lanebattery storage40permission expired7.9
Tofts Lane, Hunshelfbattery storage40approved, not built8.4
Sheephouse Heights Windfarmwind farm15refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5433, -1.7062).