Tofts Lane (40 MW battery storage)

Tofts Lane is a 40 MW battery storage project in Barnsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 7 September 2020; the record was last updated on 27 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
permission expiredstatus in REPD
27 May 2020record last updated
Barnsleycouncil area

Planning timeline

DateStage
3 May 2017Application submitted
21 July 2017Planning permission granted
7 September 2020Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
permission expired
Record last updated
27 May 2020
Operator or applicant
Enstor Power UK
Planning authority
Barnsley
Planning application reference
2017/0624
Address (REPD)
Tofts Lane, Snowden Hill, Barnsley
Council area (by location)
Barnsley
Time to decision
11 weeks
REPD reference
6942

Who decides

ApplicationsBarnsleyUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused0 of 1312%
Onshore wind refused2 of 645%
Battery storage refused0 of 516%
Median time from submission to decision21.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tofts Lane, Hunshelfbattery storage40approved, not built0.7
Sheephouse Heights Windfarmwind farm15refused1.4
Royd Moorwind farm5.9operational5.2
Spicer Hill Wind Farmwind farm6.9operational6.7
Spicer Hill Wind Farm Extensionwind farm6.9refused on appeal7.1
Blackstone Edgewind farm7.5operational7.9
Hazleheadwind farm6operational8.6
Dearne Head Wind Farmwind farm8refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4996, -1.6125).