Hazlehead (6 MW wind farm)

Hazlehead is a 6 MW wind farm project in Barnsley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 December 2011; the record was last updated on 17 May 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
17 May 2012record last updated
Barnsleycouncil area

Planning timeline

DateStage
5 September 2006Application submitted
8 March 2007Planning permission granted
1 August 2010Construction started
16 December 2011Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
17 May 2012
Operator or applicant
Banks Renewables
Planning authority
Barnsley
Planning application reference
2006/1575
Turbines
3
Address (REPD)
to the rear of Hepworth's factory, Crow Edge
Council area (by location)
Barnsley
Time to decision
26 weeks
REPD reference
3937

Who decides

ApplicationsBarnsleyUK
Decided applications (solar, wind, battery)2410,236
Refused2 (8%)19%
Solar refused0 of 1312%
Onshore wind refused2 of 645%
Battery storage refused0 of 516%
Median time from submission to decision21.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackstone Edgewind farm7.5operational2.1
Spicer Hill Wind Farm Extensionwind farm6.9refused on appeal2.6
Spicer Hill Wind Farmwind farm6.9operational2.6
Dearne Head Wind Farmwind farm8refused3.8
Royd Moorwind farm5.9operational4.1
Tofts Lanebattery storage40permission expired8.6
Sheephouse Heights Windfarmwind farm15refused8.8
Tofts Lane, Hunshelfbattery storage40approved, not built9.3