Energy Projects Near You

Dougliehill Water Treatment Works, Dougliehill Road (49 MW battery storage)

Dougliehill Water Treatment Works, Dougliehill Road is a 49 MW battery storage project in Inverclyde, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 August 2025, not yet built; the record was last updated on 21 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
approved, not builtstatus in REPD
21 November 2025record last updated
Inverclydecouncil area

Planning timeline

DateStage
28 February 2025Application submitted
6 August 2025Planning permission granted
6 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
approved, not built
Record last updated
21 November 2025
Operator or applicant
Bluestone Energy
Planning authority
Inverclyde
Planning application reference
25/0033/IC
Address (REPD)
Former Dougliehill Water Treatment Works, Dougliehill Road, Port Glasgow
Council area (by location)
Inverclyde
Time to decision
23 weeks
Name in REPD
Dougliehill Water Treatment Works, Dougliehill Road - Battery Storage
REPD reference
18293

Earlier applications for this site

ApplicationMWSubmittedOutcome
Dougliehill Water Treatment Works, Dougliehill Road 24/0053/IC4926 March 2024withdrawn 27 September 2024

Who decides

ApplicationsInverclydeUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused0 of 612%
Onshore wind refused2 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Knockair, Dougliehill Road Solar Farmsolar farm25application submitted1.0
Knockair, Dougliehill Roadbattery storage24application submitted1.0
Inverclyde Wind Farm (Corlic Hill)wind farm24operational1.9
Auchentiber Roadbattery storage700approved, not built2.0
Greenock Wind Farmwind farm55refused on appeal4.9
Flatterton Farm, Flatterton Roadbattery storage49.9approved, not built8.7
Waterhead Moorwind farm72.5application withdrawn9.3
Aggreko, Stirling Roadrooftop solar8.8application submitted9.3
Leapmoor Forestwind farm30application withdrawn9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9243, -4.7006).