Inverclyde Wind Farm (Corlic Hill) (24 MW)

Inverclyde Wind Farm (Corlic Hill) is a 24 MW wind farm project in Inverclyde, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 February 2021; the record was last updated on 12 April 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
operationalstatus in REPD
12 April 2021record last updated
Inverclydecouncil area

Planning timeline

DateStage
8 July 2013Application submitted
4 December 2014Refused by the planning authority
3 March 2015Appeal lodged
17 May 2016Planning permission granted
17 May 2016Appeal allowed
15 May 2019Construction started
20 February 2021Operational

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
12 April 2021
Operator or applicant
BayWa r.e. (formerly Forsa)
Planning authority
Inverclyde
Planning application reference
13/0199/IC
Appeal reference
PPA-280-2022
Turbines
8
Address (REPD)
Corlic Hill, near Greenock & Port Glasgow
Council area (by location)
Inverclyde
Time to decision
149 weeks
REPD reference
4200

Who decides

ApplicationsInverclydeUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused0 of 612%
Onshore wind refused2 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dougliehill Water Treatment Works, Dougliehill Roadbattery storage49approved, not built1.9
Knockair, Dougliehill Road Solar Farmsolar farm25application submitted2.2
Knockair, Dougliehill Roadbattery storage24application submitted2.2
Auchentiber Roadbattery storage700approved, not built2.6
Greenock Wind Farmwind farm55refused on appeal4.2
Flatterton Farm, Flatterton Roadbattery storage49.9approved, not built7.0
Waterhead Moorwind farm72.5application withdrawn7.9
Leapmoor Forestwind farm30application withdrawn8.1
Berfern Farmbattery storage5permission expired9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9185, -4.7289).