Renewable energy projects in Inverclyde

18 solar, wind or battery projects of 150 kW or more are located in Inverclyde (REPD, July 2026 extract): 4 pending, 9 approved but not running, 1 operational and 2 refused. The council refused 2 of 10 decided applications (20%; UK 19%), with a median 12 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects in the council area
4awaiting a decision
9approved, not running
20%of decisions refused

How Inverclyde decides

ApplicationsInverclydeUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused0 of 612%
Onshore wind refused2 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in Inverclyde

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Auchentiber Roadbattery storagebattery storage700approved, not builtupdated Sep 2024Nov 2023granted Sep 2024Sep 2024
Greenock Wind Farmwind farmwind farm55refused on appealupdated Jan 2010May 2003refused Apr 2005Jan 2010
Flatterton Farm, Flatterton Roadbattery storagebattery storage49.9approved, not builtupdated Jun 2024Oct 2023granted Jun 2024Jun 2024
Dougliehill Water Treatment Works, Dougliehill Roadbattery storagebattery storage49approved, not builtupdated Nov 2025Feb 2025granted Aug 2025Nov 2025
Leapmoor Forestwind farmwind farm30application withdrawnupdated Mar 2011Jul 2006—Mar 2011
Knockair, Dougliehill Road Solar Farmsolar farmsolar farm25application submittedupdated Dec 2025Aug 2025—Dec 2025
Inverclyde Wind Farm (Corlic Hill)wind farmwind farm24operationalupdated Apr 2021Jul 2013granted May 2016Apr 2021
Knockair, Dougliehill Roadbattery storagebattery storage24application submittedupdated Dec 2025Aug 2025—Dec 2025
Berfern Farmbattery storagebattery storage5permission expiredupdated Jul 2020May 2018—Jul 2020
Priestside Farmwind farmwind farm1.8refusedupdated Jul 2013Feb 2013refused Apr 2013Jul 2013
Kip Water Hydro Schemebattery storagebattery storage1application submitted may be out of dateupdated Dec 2018Oct 2018—Dec 2018
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Overton Water Treatment Works, Old Largs Road By Overtonrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Mar 2023Nov 2022granted Jan 2023Mar 2023
Tesco Stores, Greenock Roadrooftop solarrooftop solar0.6approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026
Faulds Park Road- Solar PV Panlelsrooftop solarrooftop solar0.3under constructionupdated Apr 2022Apr 2022granted Jul 2022Apr 2022
Greenock Headworks, Eldon Streetrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2023Oct 2022granted Dec 2022Jan 2023
Finlaystone House, Estate Greenock Roadsolar farmsolar farm0.1approved, not builtupdated Jul 2024Apr 2024granted May 2024Jul 2024
King Street - Photovoltaic Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Nov 2021Nov 2021granted Jun 2022Nov 2021
Crawfurd Streetrooftop solarrooftop solar—application submittedJun 2026——

Postcode districts in Inverclyde

DistrictProjects within 10 kmPendingApprovedOperational
PA13204102
PA1417591
PA1522591
PA1623781
PA1810140
PA1922791

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Inverclyde by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.