Energy Projects Near You

EV Charging Station Development in Toomebridge (45 MW battery storage)

EV Charging Station Development in Toomebridge is a 45 MW battery storage project in Mid Ulster, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 October 2025, not yet built; the record was last updated on 5 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
approved, not builtstatus in REPD
5 December 2025record last updated
Mid Ulstercouncil area

Planning timeline

DateStage
9 August 2024Application submitted
15 October 2025Planning permission granted
15 October 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
5 December 2025
Operator or applicant
Heron Storage Limited
Planning authority
Mid Ulster
Planning application reference
LA09/2024/0937/F
Address (REPD)
Lands Within Creagh Business Park, Toomebridge
Council area (by location)
Mid Ulster
Time to decision
62 weeks
REPD reference
17038

Who decides

ApplicationsMid UlsterUK
Decided applications (solar, wind, battery)4910,236
Refused8 (16%)19%
Solar refused0 of 912%
Onshore wind refused8 of 3345%
Battery storage refused0 of 716%
Median time from submission to decision68.9 weeks17.0 weeks
Appeals lodged / allowed5 / 1—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.758, -6.4729).