Garranbane Wind Farm (8 MW)
Garranbane Wind Farm is an 8 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 9 December 2015.
8 MWwind farm
appeal withdrawnstatus in REPD
9 December 2015record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 November 2013 | Application submitted |
| 20 July 2015 | Refused by the planning authority |
| 29 July 2015 | Appeal lodged |
| 24 November 2015 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 8 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 9 December 2015
- Operator or applicant
- Garranbane Wind Farm Ltd
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- L/2013/0622/F
- Appeal reference
- 2015/A0098
- Turbines
- 4
- Address (REPD)
- Land approximately 1.5km west of Tempo, Co Fermanagh.
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 87 weeks
- REPD reference
- 4284
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3759, -7.4934).