Energy Projects Near You

Gartymore Wind Farm (10.5 MW)

Gartymore Wind Farm is a 10.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 July 1999; the record was last updated on 27 June 2003.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWwind farm
refusedstatus in REPD
27 June 2003record last updated
Highlandcouncil area

Planning timeline

DateStage
19 October 1995Application submitted
19 July 1999Refused by the planning authority

Project details

Technology
wind farm
Capacity
10.5 MW
Status (REPD)
refused
Record last updated
27 June 2003
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Highland
Planning application reference
not recorded
Turbines
14
Address (REPD)
Gartymore Estate
Council area (by location)
Highland
Time to decision
196 weeks
REPD reference
3569

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
West Garty Windfarmwind farm54refused on appeal4.0
Navidalewind farm15refused on appeal4.3
Kintradwell Lodge Wind Farmwind farm63refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.1169, -3.7194).