West Garty Windfarm (54 MW)

West Garty Windfarm is a 54 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 October 2018; the record was last updated on 27 November 2018. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54 MWwind farm
refused on appealstatus in REPD
27 November 2018record last updated
Highlandcouncil area

Planning timeline

DateStage
1 December 2014Application submitted
17 May 2016Appeal lodged
19 October 2018Refused by the planning authority
19 October 2018Appeal refused

Project details

Technology
wind farm
Capacity
54 MW
Status (REPD)
refused on appeal
Record last updated
27 November 2018
Operator or applicant
West Garty Renewables
Planning authority
Scottish Government (S36)
Planning application reference
EC00002075
Appeal reference
WIN-270-6
Turbines
18
Turbine height
120 m
Address (REPD)
West Garty Estate, Helmsdale, East Sutherland
Council area (by location)
Highland
Time to decision
203 weeks
REPD reference
3919

Earlier applications for this site

ApplicationMWSubmittedOutcome
West Garty Wind Farm129 October 1995refused 19 July 1999

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gartymore Wind Farmwind farm10.5refused4.0
Kintradwell Lodge Wind Farmwind farm63refused5.2
Navidalewind farm15refused on appeal8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.1142, -3.7875).