Greentoft, Neven Point, Eday Wind Turbines & BESS (24 MW)
Greentoft, Neven Point, Eday Wind Turbines & BESS is a 24 MW wind farm project in Orkney Islands, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 23 June 2025, no decision recorded; the record was last updated on 11 August 2025.
24 MWwind farm
application submittedstatus in REPD
11 August 2025record last updated
Orkney Islandscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 23 June 2025 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 24 MW
- Status (REPD)
- application submitted
- Record last updated
- 11 August 2025
- Operator or applicant
- Green Power (International) Limited
- Planning authority
- Orkney Islands
- Planning application reference
- 25/203/TPPMAJ
- Turbines
- 5
- Turbine height
- 180 m
- Address (REPD)
- Greentoft, Neven Point, Eday, Orkney
- Council area (by location)
- Orkney Islands
- Name in REPD
- Greentoft, Neven Point, Eday - Wind Turbines & BESS
- REPD reference
- 19258
Recorded together with Muchalls Jnct, Muchalls (6.1 MW solar farm, application withdrawn).
Who decides
| Applications | Orkney Islands | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 29 | 10,236 |
| Refused | 5 (17%) | 19% |
| Onshore wind refused | 5 of 29 | 45% |
| Median time from submission to decision | 26.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Spurness Wind Farm | wind farm | 11 | decommissioned | 3.7 |
| Orkney’s Community Wind Farm Project - Faray | wind farm | 28.8 | application submitted | 3.8 |
| Spurness Wind Farm Repowering | wind farm | 10 | operational | 4.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (59.2134, -2.7566).