Energy Projects Near You

Haverigg Prison (9 MW wind farm)

Haverigg Prison is a 9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 3 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
abandonedstatus in REPD
3 October 2016record last updated
Cumberlandcouncil area

Planning timeline

DateStage
23 January 2015Application submitted
10 June 2015Planning permission granted
10 June 2020Permission expired

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
abandoned
Record last updated
3 October 2016
Operator or applicant
Partnerships for Renewables
Planning authority
Cumberland
Planning application reference
4/15/2022/0F1
Turbines
5
Turbine height
100 m
Address (REPD)
Land to west & south of HMP Prison, Off North Lane, Haverigg, Millom,
Council area (by location)
Cumberland
Time to decision
20 weeks
REPD reference
5077

Earlier applications for this site

ApplicationMWSubmittedOutcome
Haverigg Prison 4/12/2251/0F1109 May 2012refused 21 December 2018

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Langthwaite Farmwind farm12application submitted2.1
Bleabeck Solar Farmsolar farm10application submitted7.4
Roanhead Farmsolar farm6.5operational7.7
Sowerby Lodge Farmsolar farm5operational8.4
Solar Farm at Bleabeck Solar Farmsolar farm10application submitted8.4
Hill Solar Farmsolar farm5application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1969, -3.3219).