Hornsea 4 offshore wind farm

Hornsea 4 is a 2,400 MW offshore wind farm with 180 turbines in English waters. Its status: consented in July 2023, but Ørsted decided on 7 May 2025 to discontinue the project in its current form, keeping the seabed rights, grid connection agreement and Development Consent Order for possible later development (Ørsted). The Renewable Energy Planning Database (July 2026 extract) still records: approved on 12 July 2023, not yet built; the record was last updated on 7 May 2025. Its REPD grid reference is 83 km from the nearest postcode on land (NR26 8AG, North Norfolk). As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010098).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2,400 MWoffshore wind farm
consented, development stoppedstatus (Ørsted; status in REPD: approved, not built)
7 May 2025record last updated
83 km from land (North Norfolk)REPD location

Consent timeline

DateStage
29 September 2021Application submitted
12 July 2023Development consent granted (Secretary of State)
7 May 2025Ørsted discontinues the project in its current form
12 July 2030Permission due to expire (unless work starts)

Status source: Ørsted. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “approved, not built”.

Project details

Technology
offshore wind farm
Capacity
2,400 MW
Turbines
180
Status
consented, development stopped (Ørsted; REPD: approved, not built)
Record last updated
7 May 2025
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010098
Nearest postcode on land
NR26 8AG (North Norfolk), 83.1 km from the REPD grid reference
Time to decision
93 weeks
Contracts for Difference
AR6
REPD reference
2473

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010098). All Energy Secretary decisions on solar and wind farms.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Hornsea 32,955under construction<0.1
Hornsea 1 - Heron & Njord1,218operational<0.1

All offshore wind farms in UK waters

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.6815, 1.4207).