Behind the name Hornsea lie four different projects in the REPD, and Hornsea 1 (listed as Hornsea 1 - Heron & Njord) is the first of them. Its 174 turbines of 7 MW each are operated by Orsted. According to the July 2026 extract, of the 49 operational offshore wind farms in Great Britain, only Hornsea 2 is more powerful.
The four Hornsea projects
- Hornsea 2: 1,320 MW, the most powerful of the operational ones.
- Hornsea 1: 1,218 MW, operational since 1 December 2019.
- Hornsea 3: 2,955 MW, under construction, a separate record at the same location.
- Hornsea 4: 2,400 MW, approved, but in May 2025 Orsted halted the project.
Consent and distance to shore
The application was submitted on 30 July 2013, the examination was conducted by the Planning Inspectorate (EN010033), and the development consent order for a nationally significant infrastructure project (DCO) was granted on 10 December 2014, 71 weeks later. Construction began on 26 January 2018. The REPD measures the 83 km distance as a straight line from a single notional point covering the whole wind farm to the nearest postcode, and that postcode turned out to be in North Norfolk. The record was last updated on 3 September 2020.