Energy Projects Near You

Hornsea 1 - Heron & Njord offshore wind farm

Hornsea 1 - Heron & Njord is a 1,218 MW offshore wind farm with 174 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2019; the record was last updated on 3 September 2020. Its REPD grid reference is 83 km from the nearest postcode on land (NR26 8AG, North Norfolk). As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010033).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,218 MWoffshore wind farm
operationalstatus in REPD
3 September 2020record last updated
83 km from land (North Norfolk)REPD location

Consent timeline

DateStage
30 July 2013Application submitted
10 December 2014Development consent granted (Secretary of State)
26 January 2018Construction started
1 December 2019Operational

Project details

Technology
offshore wind farm
Capacity
1,218 MW
Turbines
174
Turbine capacity
7 MW
Status (REPD)
operational
Record last updated
3 September 2020
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010033
Nearest postcode on land
NR26 8AG (North Norfolk), 83.1 km from the REPD grid reference
Time to decision
71 weeks
Contracts for Difference
AR3
REPD reference
2525

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010033). All Energy Secretary decisions on solar and wind farms.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Hornsea 32,955under construction<0.1
Hornsea 42,400approved, not built<0.1

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.6815, 1.4207).

Behind the name Hornsea lie four different projects in the REPD, and Hornsea 1 (listed as Hornsea 1 - Heron & Njord) is the first of them. Its 174 turbines of 7 MW each are operated by Orsted. According to the July 2026 extract, of the 49 operational offshore wind farms in Great Britain, only Hornsea 2 is more powerful.

The four Hornsea projects

The application was submitted on 30 July 2013, the examination was conducted by the Planning Inspectorate (EN010033), and the development consent order for a nationally significant infrastructure project (DCO) was granted on 10 December 2014, 71 weeks later. Construction began on 26 January 2018. The REPD measures the 83 km distance as a straight line from a single notional point covering the whole wind farm to the nearest postcode, and that postcode turned out to be in North Norfolk. The record was last updated on 3 September 2020.