Hyndburn Wind Farm (24 MW)

Hyndburn Wind Farm is a 24 MW wind farm project in Hyndburn, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 October 2012; the record was last updated on 3 May 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
operationalstatus in REPD
3 May 2013record last updated
Hyndburncouncil area

Planning timeline

DateStage
1 December 2009Application submitted
17 October 2010Planning permission granted
1 April 2012Construction started
19 October 2012Operational

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
3 May 2013
Operator or applicant
Energiekontor UK
Planning authority
Hyndburn
Planning application reference
11/09/0512
Turbines
12
Address (REPD)
Hyndburn Wind Farm on Oswaldtwistle Moor
Council area (by location)
Hyndburn
Time to decision
46 weeks
REPD reference
3748

Who decides

ApplicationsHyndburnUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1412%
Onshore wind refused0 of 245%
Battery storage refused1 of 216%
Median time from submission to decision10.6 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

UK: all UK planning authorities. Counted under these REPD planning authority names: Hyndburn, Hyndburn Borough.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hyndburn Wind Farm Extensionwind farm8.2approved, not built0.6
Ramsclough Farm, Haslingden Old Road Solar Farmsolar farm26.4application submitted1.5
Knuzden Moss Farm, Oswaldtwistlebattery storage60approved, not built4.3
Davies Road - Whitebirk Battery Storagebattery storage25approved, not built5.8
Rochdale Road, Edenfieldbattery storage85refused7.7
Huncoat Power Stationbattery storage45refused8.0
Hameldon Hill extensionwind farm7.5operational8.3
Hameldon Hill Wind Farm (extension 2)wind farm7.1permission expired8.7
Shuttleworth House, Higher Shuttleworthbattery storage100refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7143, -2.389).