Langley Priory, Walnut Yard (Phase 2) (6.2 MW solar farm)

Langley Priory, Walnut Yard (Phase 2) is a 6.2 MW solar farm project in North West Leicestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2016; the record was last updated on 17 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
17 September 2018record last updated
North West Leicestershirecouncil area

Planning timeline

DateStage
6 May 2014Application submitted
7 October 2014Planning permission granted
1 December 2014Construction started
1 June 2016Operational

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
17 September 2018
Operator or applicant
Lark Energy
Planning authority
North West Leicestershire
Planning application reference
14/00408/FULM
Site area
19.5 ha
Address (REPD)
Land To The West Of Gelscoe House Farm Outbuildings Gelscoe Lane Diseworth
Council area (by location)
North West Leicestershire
Time to decision
22 weeks
REPD reference
5119

Who decides

ApplicationsNorth West LeicestershireUK
Decided applications (solar, wind, battery)3910,236
Refused2 (5%)19%
Solar refused2 of 3512%
Onshore wind refused0 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leicestershire, North West Leicestershire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lane East of Drakelow Roadsolar farm5refused4.0
East Midlands Distribution Centrerooftop solar6.1operational5.7
Long Whatton Solar Farmsolar farm49.9approved, not built6.8
Remembrance Waybattery storage99approved, not built7.6
Lockington Solar Parksolar farm15permission expired8.8
Church Farm, Kingston On Soar Solar Photovoltaic Farmsolar farm49.9approved, not built9.0
Ratcliffe On Soar Power Station Solar Farmsolar farm9approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7997, -1.3642).