Longburn Wind Farm (23 MW)

Longburn Wind Farm is a 23 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 14 May 2019; the record was last updated on 27 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23 MWwind farm
refused on appealstatus in REPD
27 June 2019record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
21 June 2016Application submitted
13 September 2017Refused by the planning authority
25 October 2017Appeal lodged
14 May 2019Appeal refused

Project details

Technology
wind farm
Capacity
23 MW
Status (REPD)
refused on appeal
Record last updated
27 June 2019
Operator or applicant
Burcote Wind
Planning authority
Dumfries and Galloway
Planning application reference
16/P/2/0187
Appeal reference
PPA-170-2129
Turbines
10
Turbine height
134 m
Address (REPD)
Carsphairn, 7.2km East of, Castle Douglas
Council area (by location)
Dumfries and Galloway
Time to decision
64 weeks
REPD reference
6176

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Quantans Hill Wind Farmwind farm96application submitted2.9
Quantans Hill Wind Farmwind farm57application withdrawn3.6
Shepherd's Rig Wind Farmwind farm81approved, not built6.5
Benbrack Wind Farmwind farm67.1operational9.7
Glenshimmeroch Wind Farmwind farm36approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1866, -4.2532).