Energy Projects Near You

Glenshimmeroch Wind Farm (36 MW)

Glenshimmeroch Wind Farm is a 36 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 September 2019, not yet built; the record was last updated on 2 January 2024. REPD also records that the planning permission expired on 4 September 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
approved, not builtmay be out of datestatus in REPD
2 January 2024record last updated
Dumfries and Gallowaycouncil area

REPD also records that the planning permission expired on 4 September 2022, so the project may not go ahead in this form.

Planning timeline

DateStage
2 July 2018Application submitted
22 February 2019Appeal lodged
5 March 2019Refused by the planning authority
4 September 2019Planning permission granted
4 September 2019Appeal allowed
4 September 2022Permission expired

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
2 January 2024
Operator or applicant
EnergieKontor UK
Planning authority
Dumfries and Galloway
Planning application reference
18/0992/FUL
Appeal reference
PPA-170-2138
Turbines
10
Turbine height
200 m
Address (REPD)
Land At Glenshimmeroch Hill, St. John's Town of Dalry, Dalry, Castle Douglas
Council area (by location)
Dumfries and Galloway
Time to decision
61 weeks
REPD reference
6444

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Margree Windfarmwind farm49.9approved, not built1.9
Troston Lochwind farm67.2approved, not built3.4
Troston Loch Wind Farmbattery storage20approved, not built3.4
Loch Hill Wind Farmwind farm28.8refused on appeal3.5
Cornharrow Wind Farmwind farm38.4approved, not built5.2
Knockman Hill, Milnmark Farmwind farm5approved, not built5.3
Longburn Wind Farmwind farm72application withdrawn6.6
Blackcraigwind farm52.9operational6.9
Shepherd's Rig Wind Farmwind farm81approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1657, -4.1048).