North Rhins (22 MW wind farm)

North Rhins is a 22 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2010; the record was last updated on 5 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
operationalstatus in REPD
5 January 2015record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
15 January 2007Application submitted
14 March 2008Planning permission granted
1 October 2009Construction started
20 January 2010Operational

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
5 January 2015
Operator or applicant
Greencoat UK Wind
Planning authority
Dumfries and Galloway
Planning application reference
not recorded
Turbines
11
Address (REPD)
North Rhins Stranraer Dumfries and Galloway
Council area (by location)
Dumfries and Galloway
Time to decision
61 weeks
REPD reference
4508

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craigenlee Wind Farmwind farm7.8application withdrawn1.0
Larbrax Wind Farmbattery storage10application submitted4.9
Larbrax Wind Farmwind farm19.2application submitted4.9
Wind Farm at 14km E/O Craig Nab Wind Energy Hubwind farm33application submitted4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8771, -5.0881).