Queniborough wind farm (9.2 MW)

Queniborough wind farm is a 9.2 MW wind farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 February 2011; the record was last updated on 28 February 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
refusedstatus in REPD
28 February 2011record last updated
Charnwoodcouncil area

Planning timeline

DateStage
22 February 2010Application submitted
4 February 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
refused
Record last updated
28 February 2011
Operator or applicant
Private Developer
Planning authority
Charnwood
Planning application reference
P/09/2464/2
Turbines
4
Address (REPD)
off Ridgemere Lane, Queniborough, Leicester
Council area (by location)
Charnwood
Time to decision
50 weeks
REPD reference
2755

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Syston Road Solar Farmsolar farm26under construction3.8
Gypsom Solar Farmsolar farm5operational6.9
Twyford, Melton Solar Farmsolar farm10approved, not built8.1
Old Hall Solar farmsolar farm22.5approved, not built8.6
Six Hills Solar Farmsolar farm18.7operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6962, -1.044).