Syston Road Solar Farm (26 MW)

Syston Road Solar Farm is a 26 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 September 2024; the record was last updated on 22 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWsolar farm
under constructionstatus in REPD
22 October 2024record last updated
Charnwoodcouncil area

Planning timeline

DateStage
8 February 2022Application submitted
12 August 2022Planning permission granted
1 September 2024Construction started

Project details

Technology
solar farm
Capacity
26 MW
Status (REPD)
under construction
Record last updated
22 October 2024
Operator or applicant
Barber Farm Partnership
Planning authority
Charnwood
Planning application reference
P/21/2661/2
Site area
46.2 ha
Address (REPD)
Syston Road
Council area (by location)
Charnwood
Time to decision
26 weeks
Contracts for Difference
AR6
Name in REPD
Syston Road - Solar Farm
REPD reference
8336

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gypsom Solar Farmsolar farm5operational3.5
Queniborough wind farmwind farm9.2refused3.8
Land at Mill Farmsolar farm7.1permission expired6.3
Poole Farm, Quorn Solar Farmsolar farm10approved, not built6.9
Land South of Melton Rdsolar farm5refused8.1
Moor Lanesolar farm5.8application withdrawn8.2
Melton Roadsolar farm5abandoned8.4
Old Hall Solar farmsolar farm22.5approved, not built8.5
Nottingham Road Solar Farmsolar farm34approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7104, -1.0959).