Energy Projects Near You

Poole Farm, Quorn Solar Farm (10 MW)

Poole Farm, Quorn Solar Farm is a 10 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 June 2022, not yet built; the record was last updated on 4 March 2022. REPD also records that the planning permission expired on 15 August 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtmay be out of datestatus in REPD
4 March 2022record last updated
Charnwoodcouncil area

REPD also records that the planning permission expired on 15 August 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
22 February 2022Application submitted
21 June 2022Planning permission granted
15 August 2025Permission expired

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
4 March 2022
Operator or applicant
Leicestershire County Council
Planning authority
Charnwood
Planning application reference
2022/Reg3Ma/0010/LCC
Site area
22.3 ha
Address (REPD)
Poole Farm, Barrow Road, Quorn
Council area (by location)
Charnwood
Time to decision
17 weeks
Name in REPD
Poole Farm, Quorn - Solar Farm
REPD reference
10721

Earlier applications for this site

ApplicationMWSubmittedOutcome
Pool Farm 2020/REG3MA/0057/LCC105 May 2020withdrawn 21 February 2022

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moor Lanesolar farm5.8application withdrawn1.4
Land at Mill Farmsolar farm7.1permission expired1.9
Nottingham Road Solar Farmsolar farm34approved, not built2.2
Gypsom Solar Farmsolar farm5operational3.9
Barn Farm (Stanford On Soar)solar farm30refused on appeal5.7
Melton Roadsolar farm5abandoned6.1
Land South of Melton Rdsolar farm5refused6.3
Wymeswold Airfieldsolar farm34operational6.7
Syston Road Solar Farmsolar farm26under construction6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7544, -1.1691).