Land at Mill Farm (7.1 MW solar farm)

Land at Mill Farm is a 7.1 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 15 August 2020; the record was last updated on 3 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.1 MWsolar farm
permission expiredstatus in REPD
3 September 2020record last updated
Charnwoodcouncil area

Planning timeline

DateStage
23 June 2015Application submitted
15 August 2017Planning permission granted
15 August 2020Permission expired

Project details

Technology
solar farm
Capacity
7.1 MW
Status (REPD)
permission expired
Record last updated
3 September 2020
Operator or applicant
TGC Renewables
Planning authority
Charnwood
Planning application reference
P/15/1054/2
Site area
14.5 ha
Address (REPD)
Land at Mill Farm, Nottingham Road, Loughborough, Leicestershire
Council area (by location)
Charnwood
Time to decision
112 weeks
REPD reference
5434

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Poole Farm, Quorn Solar Farmsolar farm10approved, not built1.9
Moor Lanesolar farm5.8application withdrawn3.1
Nottingham Road Solar Farmsolar farm34approved, not built3.9
Gypsom Solar Farmsolar farm5operational4.1
Syston Road Solar Farmsolar farm26under construction6.3
Charley Road Solar Farmsolar farm49.9application submitted6.8
Barn Farm (Stanford On Soar)solar farm30refused on appeal7.2
Melton Roadsolar farm5abandoned7.7
Land South of Melton Rdsolar farm5refused7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7384, -1.1773).