Energy Projects Near You

Nottingham Road Solar Farm (34 MW)

Nottingham Road Solar Farm is a 34 MW solar farm project in Charnwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 March 2023, not yet built; the record was last updated on 2 May 2023. REPD records the planning permission as expiring on 30 March 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34 MWsolar farm
approved, not builtmay be out of datestatus in REPD
2 May 2023record last updated
Charnwoodcouncil area

REPD records the planning permission as expiring on 30 March 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
22 December 2021Application submitted
30 March 2023Planning permission granted
30 March 2026Permission expired

Project details

Technology
solar farm
Capacity
34 MW
Status (REPD)
approved, not built
Record last updated
2 May 2023
Operator or applicant
NextPower SPV 9 Limited
Planning authority
Charnwood
Planning application reference
P/21/2160/2
Site area
44.5 ha
Address (REPD)
The E/O Loughborough on the South side of A60/Nottingham Road Loughborough
Council area (by location)
Charnwood
Time to decision
66 weeks
Contracts for Difference
AR5
Name in REPD
Nottingham Road - Solar Farm
REPD reference
10177

Who decides

ApplicationsCharnwoodUK
Decided applications (solar, wind, battery)3010,236
Refused4 (13%)19%
Solar refused2 of 2012%
Onshore wind refused2 of 345%
Battery storage refused0 of 716%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moor Lanesolar farm5.8application withdrawn0.8
Poole Farm, Quorn Solar Farmsolar farm10approved, not built2.2
Barn Farm (Stanford On Soar)solar farm30refused on appeal3.5
Land at Mill Farmsolar farm7.1permission expired3.9
Wymeswold Airfieldsolar farm34operational5.6
Gypsom Solar Farmsolar farm5operational5.6
Melton Roadsolar farm5abandoned5.9
Solar Farm at E/O Wymeswoldsolar farm49.9application submitted6.0
Long Whatton Solar Farmsolar farm49.9approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7733, -1.1791).