Energy Projects Near You

Ray Wind Farm (54.4 MW)

Ray Wind Farm is a 54.4 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 February 2017; the record was last updated on 30 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54.4 MWwind farm
operationalstatus in REPD
30 October 2017record last updated
Northumberlandcouncil area

Planning timeline

DateStage
12 December 2005Application submitted
11 November 2010Planning permission granted
1 July 2015Construction started
5 February 2017Operational

Project details

Technology
wind farm
Capacity
54.4 MW
Status (REPD)
operational
Record last updated
30 October 2017
Operator or applicant
Vattenfall
Planning authority
Northumberland
Planning application reference
06/00023/CPC
Turbines
16
Address (REPD)
Kirkwhelpington, Newcastle-upon-Tyne, Tyne and Wear
Council area (by location)
Northumberland
Time to decision
256 weeks
REPD reference
4026

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ray Battery Storage Facilitybattery storage20operational1.9
Steadings Wind Farmwind farm66refused5.0
Green Riggwind farm36operational6.6
Kirkharle Wind Farmwind farm20refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.1822, -2.0714).