Energy Projects Near You

Solar, wind and battery projects near Newcastle upon Tyne (NE19)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE19 (Northumberland): 3 operational. The largest scheme is Steadings Wind Farm (66 MW wind farm, refused on 25 March 2010), 6.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
0approved, not running
3operational

Projects within 10 km of NE19

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ray Wind Farmwind farmwind farm54.4operationalupdated Oct 2017Dec 2005granted Nov 2010Oct 2017Northumberland1.8
Ray Battery Storage Facilitybattery storagebattery storage20operationalupdated Mar 2023May 2017granted Oct 2021Mar 2023Northumberland2.0
Green Riggwind farmwind farm36operationalupdated Dec 2014Jan 2006granted Mar 2010Dec 2014Northumberland5.5
Steadings Wind Farmwind farmwind farm66refusedupdated Apr 2010Apr 2006refused Mar 2010Apr 2010Northumberland6.3
Kirkharle Wind Farmwind farmwind farm20refusedupdated Nov 2011Nov 2008refused Sep 2010Nov 2011Northumberland8.7

Distance from the average position of the NE19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm400220
Battery storage100100

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.