Energy Projects Near You

Wooperton Station, Wooperton Solar Farm (5.6 MW)

Wooperton Station, Wooperton Solar Farm is a 5.6 MW solar farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2022; the record was last updated on 5 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWsolar farm
under constructionstatus in REPD
5 July 2022record last updated
Northumberlandcouncil area

Planning timeline

DateStage
1 October 2022Construction started
16 February 2023Application submitted
5 October 2023Planning permission granted

Project details

Technology
solar farm
Capacity
5.6 MW
Status (REPD)
under construction
Record last updated
5 July 2022
Operator or applicant
A&J Scott
Planning authority
Northumberland
Planning application reference
23/00545/RENE
Site area
5.5 ha
Address (REPD)
North East Of Wooperton Station Wooperton
Council area (by location)
Northumberland
Time to decision
33 weeks
Name in REPD
Wooperton Station, Wooperton - Solar Farm
REPD reference
11589

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.472, -1.9222).