Energy Projects Near You

Solar, wind and battery projects near Bolton (BL7)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BL7 (Bolton): 1 is waiting for a planning decision, 11 approved but not yet running, 3 operational. The largest live scheme is Hyndburn Wind Farm Extension (8.2 MW wind farm, approved on 26 June 2015, not yet built; REPD status may be out of date), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
1awaiting a decision
11approved, not running
3operational

Projects within 10 km of BL7

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Stables (Edgeworth)wind farmwind farm2.6refusedupdated Nov 2007Jul 2003refused Oct 2004Nov 2007Blackburn with Darwen2.6
Union Court Storage Facilitybattery storagebattery storage4.8approved, not built may be out of dateupdated Dec 2021Jul 2021granted Oct 2021Dec 2021Bolton4.6
Hoddlesdon Mosswind farmwind farm2.7application withdrawnupdated May 2017Jun 2016—May 2017Blackburn with Darwen5.5
Salford Roadrooftop solarrooftop solar1.6operationalupdated Jun 2016——Jun 2016Bolton5.8
Edbro, Lever Streetrooftop solarrooftop solar1.7approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Bolton7.1
Rochdale Road, Edenfieldbattery storagebattery storage85refusedupdated Oct 2025Apr 2025refused Sep 2025Oct 2025Rossendale8.8
Tesco Superstore, Mansell Wayrooftop solarrooftop solar1.1application submittedupdated May 2026Apr 2026—May 2026Bolton9.1
Lascar Worksbattery storagebattery storage20operationalupdated Jul 2019Nov 2017granted May 2018Jul 2019Bury9.2
Hyndburn Wind Farmwind farmwind farm24operationalupdated May 2013Dec 2009granted Oct 2010May 2013Hyndburn9.4
Hyndburn Wind Farm Extensionwind farmwind farm8.2approved, not built may be out of dateupdated Feb 2026Jul 2014granted Jun 2015Feb 2026Hyndburn10.0
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crompton Health Centre, Crompton Wayrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024Bolton3.8
Vernacare, Folds Roadrooftop solarrooftop solar0.7approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Bolton5.3
Crown Paints, Hollins Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Feb 2023granted Apr 2023Jun 2023Blackburn with Darwen7.7
Churchill Unit Oncology Royal Bolton Hospitalrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Bolton8.7
Albion Mill, Cawdor Streetrooftop solarrooftop solar0.5approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Bolton8.7
Tesco, Mansell Wayrooftop solarrooftop solar0.5approved, not builtupdated Sep 2021Sep 2020granted Nov 2020Sep 2021Bolton9.1
Seddon Construction, Plodder Lanesolar farmsolar farm0.2approved, not builtupdated Jun 2025Jan 2025granted May 2025Jun 2025Bolton9.3
Balle Streetbattery storagebattery storage—under constructionupdated Nov 2021Oct 2017granted Nov 2021Nov 2021Blackburn with Darwen9.5

Distance from the average position of the BL7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Rooftop solar917105.1
Wind farm401118.2
Battery storage402114.8

MW in pipeline: pending, approved and under-construction capacity.

How Bolton decides solar, wind and battery applications

ApplicationsBoltonUK
Decided applications (solar, wind, battery)2210,236
Refused4 (18%)19%
Solar refused1 of 1512%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Bolton

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BL7, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.