Solar, wind and battery projects near Kirkby Stephen (CA17)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA17 (Westmorland and Furness): 1 approved but not yet running. The largest live scheme is Kirkby Stephen Grammar School, Christian Head (0.2 MW rooftop solar, approved on 14 January 2026, not yet built), 0.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of CA17

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sandwath Farmsolar farmsolar farm5.5application withdrawnupdated Jan 2016Aug 2015—Jan 2016Westmorland and Furness1.1
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kirkby Stephen Grammar School, Christian Headrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Westmorland and Furness0.6

Distance from the average position of the CA17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Rooftop solar101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.