Solar, wind and battery projects near Penrith (CA10)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA10 (Westmorland and Furness): 5 approved but not yet running. The largest live scheme is Omega Proteins Solar Farm & Battery Storage (2.5 MW solar farm, approved on 19 May 2023, not yet built; REPD status may be out of date), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CA10
Projects of 1 MW and more (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Graham Woodsolar farm | solar farm | 4.9 | abandonedupdated Mar 2019 | Aug 2015 | granted Jan 2017 | Mar 2019 | Westmorland and Furness | 2.2 |
| Land To The South Of Dallan Bank Woodsolar farm | solar farm | 4.9 | abandonedupdated Mar 2019 | Aug 2015 | granted Jan 2017 | Mar 2019 | Westmorland and Furness | 2.2 |
| Weltree Browsolar farm | solar farm | 5 | refused on appealupdated Nov 2016 | Aug 2015 | refused Dec 2015 | Nov 2016 | Westmorland and Furness | 4.8 |
| Whitestone Solar Farmsolar farm | solar farm | 5 | refusedupdated Jan 2016 | Aug 2015 | refused Dec 2015 | Jan 2016 | Westmorland and Furness | 5.2 |
| Towcett Farmsolar farm | solar farm | 4.9 | abandonedupdated Mar 2019 | Aug 2015 | granted Jan 2017 | Mar 2019 | Westmorland and Furness | 5.2 |
| Hoff Moorwind farm | wind farm | 9 | refusedupdated Apr 2008 | Jan 2003 | refused Feb 2007 | Apr 2008 | Westmorland and Furness | 7.3 |
| Trainriggs Shap Solar Farm & Battery Storagesolar farm | solar farm | 37 | refusedupdated Mar 2026 | Dec 2024 | refused Feb 2026 | Mar 2026 | Westmorland and Furness | 8.9 |
| Long Martonsolar farm | solar farm | 5 | refusedupdated Mar 2015 | Oct 2015 | refused Feb 2016 | Mar 2015 | Westmorland and Furness | 9.1 |
| Omega Proteins Solar Farm & Battery Storagesolar farm | solar farm | 2.5 | approved, not built may be out of dateupdated May 2024 | Aug 2021 | granted May 2023 | May 2024 | Westmorland and Furness | 9.3 |
| Grisewind farm | wind farm | 27 | refused on appealupdated Feb 2012 | Jan 2006 | refused Jan 2009 | Feb 2012 | Westmorland and Furness | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Penrith Leisure Centrerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Westmorland and Furness | 8.0 |
| Trainriggs Shap Solar Farm & Battery Storagebattery storage | battery storage | — | refusedupdated Mar 2026 | Dec 2024 | refused Feb 2026 | Mar 2026 | Westmorland and Furness | 8.9 |
| White Gate Caravan Park, Long Martonsolar farm | solar farm | — | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Westmorland and Furness | 9.0 |
| Beaver Lodge, Salkeld Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Mar 2025 | Mar 2025 | Westmorland and Furness | 9.3 |
| Omega Proteins Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated May 2024 | Aug 2021 | granted May 2023 | May 2024 | Westmorland and Furness | 9.3 |
Distance from the average position of the CA10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 0 | 3 | 0 | 4 | 2.9 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.1 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Battery storage | 2 | 0 | 1 | 0 | 1 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Westmorland and Furness decides solar, wind and battery applications
| Applications | Westmorland and Furness | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 30 (44%) | 19% |
| Solar refused | 14 of 42 | 12% |
| Onshore wind refused | 14 of 19 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 34.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 9 / 9 | — |
All projects in Westmorland and Furness
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.