Energy Projects Near You

Whitestone Solar Farm (5 MW)

Whitestone Solar Farm is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 December 2015; the record was last updated on 6 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
6 January 2016record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
17 August 2015Application submitted
17 December 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
6 January 2016
Operator or applicant
New Energy for the World
Planning authority
Westmorland and Furness
Planning application reference
15/0665
Site area
12.3 ha
Address (REPD)
Land To The S Of Morland and, E Of Newby, Newby, Penrith
Council area (by location)
Westmorland and Furness
Time to decision
17 weeks
REPD reference
5708

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Weltree Browsolar farm5refused on appeal0.9
Hoff Moorwind farm9refused3.1
Trainriggs Shap Solar Farm & Battery Storagesolar farm37refused5.1
Long Martonsolar farm5refused8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5756, -2.6118).