Weltree Brow (5 MW solar farm)
Weltree Brow is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 November 2016; the record was last updated on 29 November 2016.
5 MWsolar farm
refused on appealstatus in REPD
29 November 2016record last updated
Westmorland and Furnesscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 August 2015 | Application submitted |
| 17 December 2015 | Refused by the planning authority |
| 8 April 2016 | Appeal lodged |
| 22 November 2016 | Appeal refused |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 29 November 2016
- Operator or applicant
- Livos Energy
- Planning authority
- Westmorland and Furness
- Planning application reference
- 15/0668
- Appeal reference
- APP/H0928/W/16/3147136
- Site area
- 12.8 ha
- Address (REPD)
- Land To The South of Willow Tree Brow, Morland, Penrith
- Council area (by location)
- Westmorland and Furness
- Time to decision
- 17 weeks
- REPD reference
- 5704
Who decides
| Applications | Westmorland and Furness | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 30 (44%) | 19% |
| Solar refused | 14 of 42 | 12% |
| Onshore wind refused | 14 of 19 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 34.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 9 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Whitestone Solar Farm | solar farm | 5 | refused | 0.9 |
| Hoff Moor | wind farm | 9 | refused | 2.9 |
| Trainriggs Shap Solar Farm & Battery Storage | solar farm | 37 | refused | 6.0 |
| Long Marton | solar farm | 5 | refused | 7.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5828, -2.607).