Energy Projects Near You

Weltree Brow (5 MW solar farm)

Weltree Brow is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 November 2016; the record was last updated on 29 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
29 November 2016record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
17 August 2015Application submitted
17 December 2015Refused by the planning authority
8 April 2016Appeal lodged
22 November 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
29 November 2016
Operator or applicant
Livos Energy
Planning authority
Westmorland and Furness
Planning application reference
15/0668
Appeal reference
APP/H0928/W/16/3147136
Site area
12.8 ha
Address (REPD)
Land To The South of Willow Tree Brow, Morland, Penrith
Council area (by location)
Westmorland and Furness
Time to decision
17 weeks
REPD reference
5704

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitestone Solar Farmsolar farm5refused0.9
Hoff Moorwind farm9refused2.9
Trainriggs Shap Solar Farm & Battery Storagesolar farm37refused6.0
Long Martonsolar farm5refused7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5828, -2.607).