Energy Projects Near You

Long Marton (5 MW solar farm)

Long Marton is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 February 2016; the record was last updated on 4 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
4 March 2015record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
7 October 2015Application submitted
24 February 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
4 March 2015
Operator or applicant
New Energy for the World
Planning authority
Westmorland and Furness
Planning application reference
15/0908
Site area
14.3 ha
Address (REPD)
Land at Long Marton, Appleby
Council area (by location)
Westmorland and Furness
Time to decision
20 weeks
REPD reference
5782

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hoff Moorwind farm9refused6.6
Weltree Browsolar farm5refused on appeal7.8
Whitestone Solar Farmsolar farm5refused8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6327, -2.522).