Energy Projects Near You

Solar, wind and battery projects near Appleby-in-Westmorland (CA16)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA16 (Westmorland and Furness): 1 approved but not yet running. The largest live scheme is White Gate Caravan Park, Long Marton ( MW solar farm, approved on 8 May 2024, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of CA16

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hoff Moorwind farmwind farm9refusedupdated Apr 2008Jan 2003refused Feb 2007Apr 2008Westmorland and Furness5.1
Long Martonsolar farmsolar farm5refusedupdated Mar 2015Oct 2015refused Feb 2016Mar 2015Westmorland and Furness6.9
Weltree Browsolar farmsolar farm5refused on appealupdated Nov 2016Aug 2015refused Dec 2015Nov 2016Westmorland and Furness7.9
Whitestone Solar Farmsolar farmsolar farm5refusedupdated Jan 2016Aug 2015refused Dec 2015Jan 2016Westmorland and Furness8.2
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
White Gate Caravan Park, Long Martonsolar farmsolar farm—approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Westmorland and Furness5.7

Distance from the average position of the CA16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401030
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Westmorland and Furness decides solar, wind and battery applications

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

All projects in Westmorland and Furness

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.