Energy Projects Near You

Hoff Moor (9 MW wind farm)

Hoff Moor is a 9 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 February 2007; the record was last updated on 22 April 2008.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
refusedstatus in REPD
22 April 2008record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
1 January 2003Application submitted
22 February 2007Refused by the planning authority

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
refused
Record last updated
22 April 2008
Operator or applicant
Npower Renewables
Planning authority
Westmorland and Furness
Planning application reference
not recorded
Turbines
3
Address (REPD)
Hoff Moor Appleby
Council area (by location)
Westmorland and Furness
Time to decision
216 weeks
REPD reference
2995

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Weltree Browsolar farm5refused on appeal2.9
Whitestone Solar Farmsolar farm5refused3.1
Long Martonsolar farm5refused6.6
Trainriggs Shap Solar Farm & Battery Storagesolar farm37refused7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5782, -2.5634).