Solar, wind and battery projects near Penrith (CA11)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA11 (Westmorland and Furness): 8 approved but not yet running, 1 operational. The largest live scheme is Omega Proteins Solar Farm & Battery Storage (2.5 MW solar farm, approved on 19 May 2023, not yet built; REPD status may be out of date), 0.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CA11
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Grisewind farm | wind farm | 27 | refused on appealupdated Feb 2012 | Jan 2006 | refused Jan 2009 | Feb 2012 | Westmorland and Furness | 0.2 |
| Omega Proteins Solar Farm & Battery Storagesolar farm | solar farm | 2.5 | approved, not built may be out of dateupdated May 2024 | Aug 2021 | granted May 2023 | May 2024 | Westmorland and Furness | 0.6 |
| Moss Thorn Farmsolar farm | solar farm | 5.8 | operationalupdated Apr 2017 | May 2015 | granted Oct 2016 | Apr 2017 | Westmorland and Furness | 1.0 |
| Silver Howe, Flusco Solar Array, Wind Turbines Battery Storagesolar farm | solar farm | 1.9 | approved, not built may be out of dateupdated Jul 2023 | Sep 2022 | granted May 2023 | Jul 2023 | Westmorland and Furness | 3.8 |
| Bowscarsolar farm | solar farm | 5 | permission expiredupdated Jun 2019 | Aug 2015 | granted Jun 2016 | Jun 2019 | Westmorland and Furness | 5.2 |
| Berrier Hillwind farm | wind farm | 22.5 | refused on appealupdated Sep 2011 | Aug 2007 | refused Jan 2009 | Sep 2011 | Westmorland and Furness | 9.0 |
| Land at Skelton Radio Transmitter Sitesolar farm | solar farm | 5 | application withdrawnupdated May 2017 | Oct 2015 | — | May 2017 | Westmorland and Furness | 9.1 |
| Town End Farmsolar farm | solar farm | 5 | permission expiredupdated May 2020 | Aug 2015 | granted Oct 2016 | May 2020 | Westmorland and Furness | 9.3 |
| Land at Calthwaitebattery storage | battery storage | 6 | permission expiredupdated Aug 2019 | Oct 2017 | granted Jan 2018 | Aug 2019 | Westmorland and Furness | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sewborwens Farmhouse, Newton Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Westmorland and Furness | 0.3 |
| Omega Proteins Solar Farm & Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated May 2024 | Aug 2021 | granted May 2023 | May 2024 | Westmorland and Furness | 0.6 |
| Penrith Leisure Centrerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Westmorland and Furness | 2.2 |
| Greengill Foot, Inglewood Road Solar Arrayssolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2025 | Nov 2024 | granted Mar 2025 | Apr 2025 | Westmorland and Furness | 3.6 |
| Silver Howe, Flusco Solar Array, Wind Turbines Battery Storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Jul 2023 | Sep 2022 | granted May 2023 | Jul 2023 | Westmorland and Furness | 3.8 |
| Beaver Lodge, Salkeld Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Mar 2025 | Mar 2025 | Westmorland and Furness | 4.0 |
Distance from the average position of the CA11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 0 | 4 | 1 | 0 | 4.9 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.3 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Battery storage | 3 | 0 | 2 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Westmorland and Furness decides solar, wind and battery applications
| Applications | Westmorland and Furness | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 30 (44%) | 19% |
| Solar refused | 14 of 42 | 12% |
| Onshore wind refused | 14 of 19 | 45% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 34.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 9 / 9 | — |
All projects in Westmorland and Furness
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CA11, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.