Energy Projects Near You

Solar, wind and battery projects near Carlisle (CA4)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CA4 (Cumberland): 2 are waiting for a planning decision, 4 approved but not yet running, 1 operational. The largest live scheme is Grassing Rome Street (15.5 MW battery storage, approved on 7 March 2024, not yet built), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
4approved, not running
1operational

Projects within 10 km of CA4

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Newlands Farm Windwind farmwind farm6.9refused on appealupdated Feb 2011Jul 2008refused Oct 2008Feb 2011Cumberland3.2
Newlands Farm 2wind farmwind farm4.6refusedupdated Aug 2012Jul 2011refused Nov 2011Aug 2012Cumberland3.2
Land at Wreaysolar farmsolar farm5operationalupdated May 2017Jul 2015granted Aug 2016May 2017Westmorland and Furness5.2
Grassing Rome Streetbattery storagebattery storage15.5approved, not builtupdated Apr 2024Jun 2022granted Mar 2024Apr 2024Cumberland7.8
Hay Close Wind Farmwind farmwind farm10appeal withdrawnupdated Oct 2015Jul 2014refused Oct 2014Oct 2015Westmorland and Furness9.4
Roxane UK, Armathwaite Solar Array & Battery Storagesolar farmsolar farm5approved, not builtupdated May 2026Aug 2025granted Mar 2026May 2026Westmorland and Furness9.5
Roxane UK, Armathwaite Solar Array & Battery Storagebattery storagebattery storage1approved, not builtupdated May 2026Aug 2025granted Mar 2026May 2026Westmorland and Furness9.5
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Head Dale, Cocklakes - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedJun 2026——Cumberland1.6
The Carleton Clinic, Cumwhinton Driverooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Cumberland4.5
Richard Rose Central Academy, Lismore Placerooftop solarrooftop solar0.3application submittedJun 2026——Cumberland7.9

Distance from the average position of the CA4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201105
Rooftop solar211000.6
Wind farm300020
Battery storage3120016.7

MW in pipeline: pending, approved and under-construction capacity.

How Cumberland decides solar, wind and battery applications

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

All projects in Cumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.