Energy Projects Near You

Newlands Farm Wind (6.9 MW)

Newlands Farm Wind is a 6.9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 15 March 2010; the record was last updated on 7 February 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refused on appealstatus in REPD
7 February 2011record last updated
Cumberlandcouncil area

Planning timeline

DateStage
10 July 2008Application submitted
13 October 2008Refused by the planning authority
15 March 2010Appeal refused

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused on appeal
Record last updated
7 February 2011
Operator or applicant
Bolsterstone Plc
Planning authority
Cumberland
Planning application reference
08/0707
Appeal reference
APP/E0915/A/09/2101659
Turbines
3
Address (REPD)
Carelton, Carlisle, Cumbria. CA4 0AE
Council area (by location)
Cumberland
Time to decision
14 weeks
REPD reference
2670

Who decides

ApplicationsCumberlandUK
Decided applications (solar, wind, battery)9110,236
Refused30 (33%)19%
Solar refused4 of 3212%
Onshore wind refused25 of 4545%
Battery storage refused1 of 1416%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed7 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grassing Rome Streetbattery storage15.5approved, not built4.6
Land at Wreaysolar farm5operational4.8
Land between Orton Park Farmsolar farm6.4operational7.3
Cargo Road, Cargobattery storage200abandoned9.5
Kingmoor Parksolar farm5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8612, -2.8756).