Newlands Farm Wind (6.9 MW)
Newlands Farm Wind is a 6.9 MW wind farm project in Cumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 15 March 2010; the record was last updated on 7 February 2011.
6.9 MWwind farm
refused on appealstatus in REPD
7 February 2011record last updated
Cumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 July 2008 | Application submitted |
| 13 October 2008 | Refused by the planning authority |
| 15 March 2010 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 6.9 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 7 February 2011
- Operator or applicant
- Bolsterstone Plc
- Planning authority
- Cumberland
- Planning application reference
- 08/0707
- Appeal reference
- APP/E0915/A/09/2101659
- Turbines
- 3
- Address (REPD)
- Carelton, Carlisle, Cumbria. CA4 0AE
- Council area (by location)
- Cumberland
- Time to decision
- 14 weeks
- REPD reference
- 2670
Who decides
| Applications | Cumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 30 (33%) | 19% |
| Solar refused | 4 of 32 | 12% |
| Onshore wind refused | 25 of 45 | 45% |
| Battery storage refused | 1 of 14 | 16% |
| Median time from submission to decision | 22.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Grassing Rome Street | battery storage | 15.5 | approved, not built | 4.6 |
| Land at Wreay | solar farm | 5 | operational | 4.8 |
| Land between Orton Park Farm | solar farm | 6.4 | operational | 7.3 |
| Cargo Road, Cargo | battery storage | 200 | abandoned | 9.5 |
| Kingmoor Park | solar farm | 5 | operational | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8612, -2.8756).