Land at Wreay (5 MW solar farm)

Land at Wreay is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 May 2017record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
31 July 2015Application submitted
29 October 2015Refused by the planning authority
12 January 2016Appeal lodged
4 August 2016Planning permission granted
4 August 2016Appeal allowed
15 December 2016Construction started
29 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Anesco
Planning authority
Westmorland and Furness
Planning application reference
15/0653
Appeal reference
APP/H0928/W/15/3140750
Site area
15.2 ha
Address (REPD)
Land At Wreay, Calthwaite, Penrith, Carlisle
Council area (by location)
Westmorland and Furness
Time to decision
53 weeks
REPD reference
5525

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newlands Farm Windwind farm6.9refused on appeal4.8
Hay Close Wind Farmwind farm10appeal withdrawn6.4
Grassing Rome Streetbattery storage15.5approved, not built7.8
Solar Panels at Devonshire Squaresolar farm30refused8.1
Land between Orton Park Farmsolar farm6.4operational8.5
Land at Calthwaitebattery storage6permission expired9.3
Roxane UK, Armathwaite Solar Array & Battery Storagesolar farm5approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8195, -2.8971).