Solar Panels at Devonshire Square (30 MW)

Solar Panels at Devonshire Square is a 30 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 March 2026; the record was last updated on 27 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
refusedstatus in REPD
27 April 2026record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
15 July 2025Application submitted
16 March 2026Refused by the planning authority

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
refused
Record last updated
27 April 2026
Operator or applicant
Noventum Power Limited
Planning authority
Westmorland and Furness
Planning application reference
2025/1267/FPA
Site area
48.4 ha
Address (REPD)
Devonshire Square, Calthwaite, Penrith
Council area (by location)
Westmorland and Furness
Time to decision
35 weeks
Name in REPD
High Rigg Solar Farm - Solar Panels
REPD reference
14881

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hay Close Wind Farmwind farm10appeal withdrawn2.3
Land at Calthwaitebattery storage6permission expired2.4
Land at Skelton Radio Transmitter Sitesolar farm5application withdrawn2.4
Town End Farmsolar farm5permission expired2.9
Lamonby Wind Farmwind farm27application withdrawn5.0
Roxane UK, Armathwaite Solar Array & Battery Storagesolar farm5approved, not built7.3
Land at Wreaysolar farm5operational8.1
Berrier Hillwind farm22.5refused on appeal9.2
Bowscarsolar farm5permission expired9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7471, -2.8791).