Energy Projects Near You

Berrier Hill (22.5 MW wind farm)

Berrier Hill is a 22.5 MW wind farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 June 2010; the record was last updated on 12 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
10 August 2007Application submitted
2 January 2009Refused by the planning authority
28 June 2010Appeal refused

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
refused on appeal
Record last updated
12 September 2011
Operator or applicant
West Coast Energy
Planning authority
Westmorland and Furness
Planning application reference
07/0636
Turbines
9
Address (REPD)
Near Greystoke
Council area (by location)
Westmorland and Furness
Time to decision
73 weeks
REPD reference
3032

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lamonby Wind Farmwind farm27application withdrawn4.7
Town End Farmsolar farm5permission expired6.2
Land at Skelton Radio Transmitter Sitesolar farm5application withdrawn6.9
Moss Thorn Farmsolar farm5.8operational8.1
Grisewind farm27refused on appeal8.9
Solar Panels at Devonshire Squaresolar farm30refused9.2
Land at Calthwaitebattery storage6permission expired9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6691, -2.9245).