Moss Thorn Farm (5.8 MW solar farm)

Moss Thorn Farm is a 5.8 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 February 2017; the record was last updated on 20 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.8 MWsolar farm
operationalstatus in REPD
20 April 2017record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
29 May 2015Application submitted
4 December 2015Refused by the planning authority
25 February 2016Appeal lodged
11 October 2016Planning permission granted
11 October 2016Appeal allowed
14 November 2016Construction started
27 February 2017Operational

Project details

Technology
solar farm
Capacity
5.8 MW
Status (REPD)
operational
Record last updated
20 April 2017
Operator or applicant
TGC Renewables
Planning authority
Westmorland and Furness
Planning application reference
15/0459
Appeal reference
APP/H0928/W/16/3143476
Site area
14.2 ha
Address (REPD)
Land near Moss Thorn Farm, Pallet Hill, Penrith
Council area (by location)
Westmorland and Furness
Time to decision
72 weeks
REPD reference
6019

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grisewind farm27refused on appeal0.8
Bowscarsolar farm5permission expired5.4
Berrier Hillwind farm22.5refused on appeal8.1
Land at Skelton Radio Transmitter Sitesolar farm5application withdrawn8.2
Town End Farmsolar farm5permission expired8.4
Land at Calthwaitebattery storage6permission expired8.7
Lamonby Wind Farmwind farm27application withdrawn9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6678, -2.7983).