Energy Projects Near You

Town End Farm (5 MW solar farm)

Town End Farm is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 11 October 2019; the record was last updated on 21 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
21 May 2020record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
14 August 2015Application submitted
29 October 2015Refused by the planning authority
8 April 2016Appeal lodged
11 October 2016Planning permission granted
11 October 2016Appeal allowed
11 October 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
21 May 2020
Operator or applicant
RALOS New Energy
Planning authority
Westmorland and Furness
Planning application reference
15/0658
Appeal reference
APP/H0928/W/16/3146738
Site area
8.8 ha
Address (REPD)
Land At Town End Farm, Skelton, Penrith
Council area (by location)
Westmorland and Furness
Time to decision
61 weeks
REPD reference
5699

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Skelton Radio Transmitter Sitesolar farm5application withdrawn0.9
Lamonby Wind Farmwind farm27application withdrawn2.5
Solar Panels at Devonshire Squaresolar farm30refused2.9
Land at Calthwaitebattery storage6permission expired3.7
Hay Close Wind Farmwind farm10appeal withdrawn5.2
Berrier Hillwind farm22.5refused on appeal6.2
Moss Thorn Farmsolar farm5.8operational8.4
Grisewind farm27refused on appeal9.2
Roxane UK, Armathwaite Solar Array & Battery Storagesolar farm5approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7216, -2.8901).